ARCHIVED: Completed project: IUB STC renovations

This content has been archived, and is no longer maintained by Indiana University. Information here may no longer be accurate, and links may no longer be available or reliable.

Primary UITS contact: Doug Grover

Completed: September 3, 2007

Description: Each summer, in addition to installing new computers on a three-year lifecycle, Student Technology Centers staff at IUPUI and IUB clean the continuing computers, install a new software build for fall semester, and arrange for minor repairs and facilities maintenance of the STCs. On roughly a ten-year lifecycle, each location receives a major renovation, with new data cabling, power, furniture, carpet, and paint. This summer at IUB, starting at the end of Summer I, three classrooms (Business 407 and 417, Fine Arts 137) and two study-only labs (Business 415, Foster Shea 015) were renovated.

Minor renovations are not tracked here, but include:

  • Ballantine 118: Network upgrade, painting, new projector controls
  • Business/SPEA Library 150: New furniture
  • Geology 226: Network upgrade, conversion from Unix to Windows classroom
  • HPER 154, 155: Network upgrade, new projector controls
  • Library 503: New furniture and network upgrade, rearrangement to match footprint of new classroom in LI402
  • Psychology 120: Network upgrade
  • Radio & TV 250: Network upgrade

Outcome: Rejuvenated surroundings, however subtly, foster an improved atmosphere for learning. Additionally, we are adding seats in the two Business classrooms, helping KSB achieve goals of instructional efficiency. In Foster Shea, the International Living-Learning Center, activity in the computer lab has increased 80% in the past two years. Residential Programs and Services is contributing the adjacent dorm room to double the size of the lab in recognition of its popularity.

Milestones and status:

  • Business 407
    June 20: Computers, furniture, electrical and network removal complete
    June 27: Wall painting complete
    July 13: New carpet installation complete
    July 20: Furniture installation complete; power/data conduit installed
    August 10: Hardware and software installed; classroom ready for use
  • Business 415
    June 20: Computers, furniture, electrical and network removal complete
    July 6: New electrical, painting underway
    July 13: New carpet installation complete
    July 20: Painting complete; furniture installation under way
    August 10: Furniture, power and data, hardware and software installed; study-only lab ready for use
  • Business 417
    June 20: Computers, furniture, electrical and network removal complete
    July 6: New electrical underway
    July 13: New carpet installation complete
    July 20: Painting complete; furniture installation under way
    August 10: Furniture, power and data, hardware and software installed; classroom lacks only the markerboard to be fully ready for use
    August 27: Classroom in production using temporary markerboards. No ETA on permanent installation.
  • Fine Arts 137
    June 20: Computers, furniture, whiteboard, electrical and network removal complete
    July 4: Carpet removal complete
    July 13: Repainting complete; electrical underway
    July 20: New carpet installation complete
    August 10: Furniture reset; new iMacs secured and ready to be installed; waiting on power, data, and electronic security in center rows to be completed, estimated to be done August 15
    August 17: Installations complete, classroom ready for use
  • Foster Shea 015
    May 11: Computers, furniture, electrical and network removal complete
    June 20: Demolition complete, door/window frames installed
    July 13: No change
    July 20: Door and window frames painted
    August 10: Window glass installed; carpet installed; data and electronic security reinstalled; furniture delivery scheduled for August 15; waiting on additional power outlets
    August 17: Tables installed
    August 23: Additional power installed
    August 24: Lab complete and ready for use

Related information: View a photo gallery of these summer renovation projects, as well as the two new classrooms under construction in Wells Library and McNutt Center.

Project team:

  • Tim Spears, STC
  • Bob Wetzel, Physical Plant
  • Kelly Reed, University Architect's Office
  • Michele Bowlen, RPS Facilities Management
  • Don Allbright, RPS Facilities Management